Carnegie Assembling CETO Unit for October Deployment
• CETO power take-off assembly underway in Germany before return to Basque Country for
ACHIEVE Programme’s ocean deployment
• Staged deployment, commissioning and testing commencing in October 2026
• Offshore deployment and onshore testing will validate 3 years of intensive project specific
design and construction of CETO technology
Carnegie Clean Energy (ASX: CCE) (“Carnegie” or the “Company”) is pleased to provide an update on
the assembly and deployment plans for the Company’s leading wave energy technology, CETO, under
the ACHIEVE Programme, which is funding CETO’s grid connected build and installation at the Biscay
Marine Energy Platform (BiMEP).
Fabrication of the ACHIEVE CETO Unit’s Power Take-Off (PTO) Modules is nearing completion in the
Basque Country, with the first of the three PTO Modules recently delivered to one of SKF’s global
manufacturing facilities in Germany, where final PTO assembly works are being undertaken.
PTO Module departing fabricator (left), illustration of three PTO Modules highlighted blue in CETO Unit (centre),
and PTO Module at SKF Assembly Hall (right)
Delivered through Carnegie’s partnership with global precision manufacturer SKF, assembly works
involve the integration of all PTO equipment into each of the three PTO Modules, including generators,
tensioners, shafts, couplings, bearings, seals, and sensors. This activity essentially connects all the
power generating equipment inside the module.
Some of the PTO Equipment ready for assembly into PTO Module
www.carnegiece.com
2
The current PTO assembly works follow on from the previously completed assembly of the Electrical
Module (EM), undertaken with SEI, a local Basque supplier. As the PTO Module assembly process
advances, system testing will be undertaken to validate communication between the EM and PTO
Modules in preparation for offshore deployment.
Electrical Module assembly works (left), illustration of Electrical Module highlighted blue in CETO Unit (centre) Carnegie
CEO, Jonathan Fievez, inside fully assembled Electrical Module (right)
Carnegie’s CEO Jonathan Fievez has recently returned from site visits to inspect assembly activities
and meet with key suppliers and stakeholders.
Jonathan Fievez said today “there is a growing sense of excitement amongst our talented team that
offshore deployment is getting closer. We look forward to meeting the goal of having our world
leading offshore power generation device in the water in 2026. Delivery of CETO will position Carnegie
at the forefront of ocean energy and provide a strong platform for commercial project opportunities
into the future.”
Carnegie will undertake a staged deployment and commissioning process for the ACHIEVE CETO Unit,
commencing with deployment of the foundations at Carnegie’s BiMEP berth in the coming quarter.
The first stage of the CETO Unit’s ocean deployment is planned for October 2026 with subsequent
ocean deployment, commissioning and testing stages progressively completing the system and
moving to optimisation.
Biscay Marine Energy Platform – site of ACHIEVE CETO Unit deployment
www.carnegiece.com
3
Carnegie is currently procuring specialist marine contractors to undertake the installation of
foundations and mooring systems, connection to the existing export cable and installation of the CETO
Unit. Timing of ocean deployment will be subject to prevailing contractor availability, supply chain and
weather conditions.
This announcement has been authorised by the Chairman and CEO.
View and engage with this announcement on Carnegie’s dedicated Investor Hub:
https://investors.carnegiece.com/link/P7QwJe
For more information
Carnegie Clean Energy Limited
+61 8 6168 8400
enquiries@carnegiece.com
www.carnegiece.com
ABOUT CARNEGIE AND ITS SUBSIDIARIES
Carnegie Clean Energy (ASX: CCE) is a technology developer focused on delivering ocean energy
technologies to make the world more sustainable. Carnegie Technologies Spain and CETO Wave
Energy Ireland are wholly owned subsidiaries of Carnegie Clean Energy. Carnegie is the owner and
developer of the CETO® and MoorPower® technologies, which capture energy from ocean waves and
convert it into electricity. Using the latest advances in artificial intelligence and electric machines,
Carnegie optimally controls our technologies and generates electricity in the most efficient way
possible. The company has a long history in ocean energy with a track record of world leading
developments. https://www.carnegiece.com
ABOUT ACHIEVE PROGRAMME
The ACHIEVE Programme is an initiative being
delivered by Carnegie’s subsidiaries CETO Wave
Energy Ireland under contract by EuropeWave Buyers
Group (ACHIEVE Project) and Carnegie Technologies
Spain with the support of funding awarded by the
Spanish Government through the RENMARINAS
Demos Programme (AGUAMARINA Project) and the
Basque Government through a grant from the Ente
Vasco de la Energia (ACHIEVE+ Project).
Through this collaborative initiative, Carnegie will
deploy and operate a CETO prototype at the Basque
Marine Energy Platform (BiMEP) in the Basque
Country, Spain, marking a key step on CETO’s
commercialisation pathway. The ACHIEVE CETO Unit will operate at this open ocean site and the data
www.carnegiece.com
4
collected will be used to validate the performance of the CETO technology and propel it along the
commercialisation pathway.
ABOUT EUROPEWAVE
EuropeWave PCP is an innovative R&D programme for wave
energy technology. It combines over €22.5m of national,
regional and EU funding to drive a competitive Pre-Commercial
Procurement (PCP) programme for wave energy.
Originally pioneered by the Wave Energy Scotland programme, the PCP model provides a structured
approach, fostering greater openness, collaboration and sharing of risk between the public sector and
technology developers. The programme will focus on the design, development, and demonstration of
cost-effective wave energy converter (WEC) systems for electrical power production that can survive
in the harsh ocean environment.
Match-funded by the EU’s Horizon 2020 programme, EuropeWave is a collaboration between Wave
Energy Scotland (WES), the Basque Energy Agency (EVE) and Ocean Energy Europe (OEE). This
collaboration is closely aligned with the decarbonisation, industrial and competitiveness objectives of
the European Green Deal, and is part of a range of actions being taken to meet the European
Commission’s targets of 100MW of ocean energy by 2027 and at least 1GW by 2030.
The EuropeWave Project has received funding from the European Union’s Horizon
2020 Research and Innovation Programme under grant agreement No 883751.
https://www.europewave.eu/
ABOUT RENMARINAS DEMOS
The RENMARINAS DEMOS Programme was established by Spain’s Ministerio para la Transición
Ecológica y el Reto Demográfico (Ministry for Ecological Transition and the Demographic Challenge)
to grant aid for investment in pilot projects, test platforms and port infrastructure for marine
renewables. This was established within the framework of the European Union-funded Recovery,
Transformation and Resilience Plan, Next Generation EU. The programme provides aid in the form of
a non-refundable grant managed by IDAE, Instituto para la Diversificación y Ahorro de la Energía
(Institute for Diversifcation and Energy Saving).
www.carnegiece.com
5
ABOUT ENTE VASCO DE LA ENERGIA (EVE)
The Ente Vasco de la Energía (EVE) is the Basque Country's energy agency, a public body established
by the Basque Government. EVE serves as a central force in the region's energy sector, with a focus
on the promotion of energy efficiency, the expansion of renewable energy sources, the development
of sustainable energy policy, and the advancement of innovative energy technologies. The funding
has been provided through the Grants programme for investment in the demonstration and validation
of emerging marine renewable energy technologies 2023 to further support the ACHIEVE Programme.
Share your feedback
Discover