Successful Stage 1 Deployment
Released
Released
Announcement PDF
ASX ANNOUNCEMENT
16 November 2026
www.carnegiece.com
1
CETO Buoyant Actuator (BA) Successfully Deployed
for Stage 1 Offshore Campaign
• Carnegie’s CETO Buoyant Actuator has been deployed and is now offshore at the Biscay Marine
Energy Platform (BiMEP) in the Basque Country, Spain
• Initial offshore campaign aims to validate port and maritime authorisation pathways, local
supply chain logistics, quayside assembly, towing, and offshore installation operations
• Retrieval window will be governed by maritime weather conditions, with retrieval planned for
the end of the current weather window
• Completion of Stage 1 offshore deployment activities unlocks Programme milestones and
funding payments to support subsequent stages of the ACHIEVE Programme
CETO BA deployed at BiMEP
Carnegie Clean Energy Limited (ASX: CCE) (“Carnegie” or the “Company”) is pleased to announce that
the ACHIEVE CETO Buoyant Actuator (BA) has been successfully deployed at the Biscay Marine Energy
Platform (BiMEP) off the coast of Armintza in the Basque Country, Spain. This is the first offshore
deployment stage to be delivered in the ACHIEVE Programme and validates key logistics and supply
chain capabilities. Undertaking this short deployment stage also delivers learnings and increases
certainty for the next stage of deployment which will entail full CETO system deployment including
grid connection.
Summary of Recent Activities
Prior to deployment, the three modular sections of the CETO BA were transported from the local
Basque fabricator to the Port of Bilbao where they were assembled quayside. The CETO BA was then
lowered by crane into the water and docked alongside the quay ready for transport to site. On
Saturday, the CETO BA was towed from the port to Carnegie’s pre-permitted offshore berth at BiMEP
where it was connected to a bespoke installed mooring and anchor system. Following the successful
www.carnegiece.com
2
deployment, the CETO BA will remain at the offshore site for a short period before being retrieved
and brought back to port at the end of the current weather window.
CETO BA sections transported from local manufacturer (top left) to port quayside for assembly (top right),
placement of anchor system (bottom left), and Carnegie team joined by Ente Vasco de la Energia (EVE)
representative and BiMEP technical team following quayside assembly (bottom right).
Key Operational Objectives and Learnings
The Stage 1 deployment is a short campaign deploying the CETO BA to validate marine procedures
and BA behaviour in real ocean conditions while under tow and at Carnegie’s BiMEP berth. The process
of deploying the CETO BA at BiMEP has provided valuable operational insights across the necessary
local and port authorisations, supply chain logistics, and offshore execution which provide increased
certainty for subsequent full CETO system operations.
As part of this first deployment, Carnegie successfully navigated and secured the necessary
operational clearances and authorisations from port and maritime authorities covering quayside
assembly, heavy lifting, port and offshore transit, and offshore installation. These activities were
valuable in establishing and validating practical local supply chain workflows and logistics.
At the Port of Bilbao and BiMEP, the team successfully coordinated and executed the anchor and
mooring system deployment, towing procedures, vessel coordination, and offshore mooring hook-up.
The activities were led by Carnegie’s Chief Technology Officer (CTO) who draws upon a wealth of
www.carnegiece.com
3
experience, gained through deploying Carnegie’s previous CETO array in Australia and leading the
CETO design and innovation process since then.
Through this hands-on marine execution, Carnegie’s entire team has gained vital local offshore
operations experience, expanding internal team capacity to manage complex offshore campaigns
within the Basque Country.
This experience provides increased technical and logistical certainty for subsequent deployments as
Carnegie prepares for the full Stage 2 grid-connected deployment scheduled for European spring
2027. In addition, the successful completion of these activities unlocks key funding milestones and
financial support under the ACHIEVE Programme’s funding framework.
CETO BA lowered quayside (top left), departing the Port of Bilbao (top right), Carnegie CTO leading
offshore activities (bottom left) and anchored at BiMEP berth (bottom right)
Next steps
The CETO BA is scheduled to remain on site for a brief period before the team retrieves the device,
again testing and validating offshore logistics and supply chain capability to bring the unit safely back
to port. The retrieval of the CETO BA and tow back to port is being scheduled around suitable weather
windows and vessel availability. The time deployed on site for Stage 1 is short given the key objectives
of Stage 1 deployment are focused on validating offshore logistics, installation and retrieval activities
as well as funding milestones.
Over the European winter months, the CETO BA will be kept onshore in the port while the PTO
Modules undergo final onshore testing locally. The onshore testing includes a series of tests with the
www.carnegiece.com
4
PTO Modules and the Electrical Module simulating real ocean conditions to validate mechanical,
electrical, control and communications functions. Following this, the Stage 2 deployment is expected
in European Spring where the fully integrated CETO system will be deployed at BiMEP and grid
connected. While the CETO system is designed to operate year-round, the standard industry practice
is to deploy and grid connect a prototype for the first time during the most benign weather conditions
(late spring – summer), enabling any troubleshooting to occur easily during the first months of
operations and progressively exposing the prototype to more extreme conditions.
Carnegie Chief Executive Officer, Jonathan Fiévez, commented:
"Seeing the CETO BA in the water offshore at the BiMEP site is a proud moment for everyone at
Carnegie. It has taken a mammoth effort from our team in Bilbao to ensure the Stage 1 deployment
has been a success. Whilst this is just the first stage of offshore campaign, the experience gained from
this short deployment has increased our team’s capabilities and put us in a much stronger, more
certain position as we push toward our full grid-connected Stage 2 deployment in European spring
2027. This is an ambitious project given the large technology leaps we’re taking so executing it in
stages and conducting substantial onshore testing are important to manage risk.”
This announcement has been authorised by the Chairman and CEO.
For more information
Carnegie Clean Energy Limited
+61 8 6168 8400
enquiries@carnegiece.com
www.carnegiece.com
ABOUT CARNEGIE AND ITS SUBSIDIARIES
Carnegie Clean Energy (ASX: CCE) is a technology developer focused on delivering ocean energy
technologies to make the world more sustainable. Carnegie Technologies Spain and CETO Wave
Energy Ireland are wholly owned subsidiaries of Carnegie Clean Energy. Carnegie is the owner and
developer of the CETO® and MoorPower® technologies, which capture energy from ocean waves and
convert it into electricity. Using the latest advances in artificial intelligence and electric machines,
Carnegie optimally controls our technologies and generates electricity in the most efficient way
possible. The company has a long history in ocean energy with a track record of world leading
developments. https://www.carnegiece.com
www.carnegiece.com
5
ABOUT ACHIEVE PROGRAMME
The ACHIEVE Programme is an initiative being
delivered by Carnegie’s subsidiaries CETO Wave
Energy Ireland under contract by EuropeWave Buyers
Group (ACHIEVE Project) and Carnegie Technologies
Spain with the support of funding awarded by the
Spanish Government through the RENMARINAS
Demos Programme (AGUAMARINA Project) and the
Basque Government through a grant from the Ente
Vasco de la Energia (ACHIEVE+ Project).
Through this collaborative initiative, Carnegie will
deploy and operate a CETO prototype at the Basque
Marine Energy Platform (BiMEP) in the Basque
Country, Spain, marking a key step on CETO’s
commercialisation pathway. The CETO Unit will operate in this open ocean site and the data collected
will be used to validate the performance of the CETO technology and propel it along the
commercialisation pathway.
ABOUT EUROPEWAVE
EuropeWave PCP is an innovative R&D programme for wave
energy technology, which runs from 2022 to 2026. It combines
over €22.5m of national, regional and EU funding to drive a
competitive Pre-Commercial Procurement (PCP) programme
for wave energy.
Originally pioneered by the Wave Energy Scotland programme, the PCP model provides a structured
approach, fostering greater openness, collaboration and sharing of risk between the public sector and
technology developers. The programme will focus on the design, development, and demonstration of
cost-effective wave energy converter (WEC) systems for electrical power production that can survive
in the harsh ocean environment.
Match-funded by the EU’s Horizon 2020 programme, EuropeWave is a collaboration between Wave
Energy Scotland (WES), the Basque Energy Agency (EVE) and Ocean Energy Europe (OEE). This
collaboration is closely aligned with the decarbonisation, industrial and competitiveness objectives of
the European Green Deal, and is part of a range of actions being taken to meet the European
Commission’s targets of 100MW of ocean energy by 2027 and at least 1GW by 2030.
The EuropeWave Project has received funding from the European Union’s Horizon
2020 Research and Innovation Programme under grant agreement No 883751.
https://www.europewave.eu/
www.carnegiece.com
6
ABOUT RENMARINAS DEMOS
The RENMARINAS DEMOS Programme was established by Spain’s Ministerio para la Transición
Ecológica y el Reto Demográfico (Ministry for Ecological Transition and the Demographic Challenge)
to grant aid for investment in pilot projects, test platforms and port infrastructure for marine
renewables. This was established within the framework of the European Union-funded Recovery,
Transformation and Resilience Plan, Next Generation EU. The programme provides aid in the form of
a non-refundable grant managed by IDAE, Instituto para la Diversificación y Ahorro de la Energía
(Institute for Diversifcation and Energy Saving).
ABOUT ENTE VASCO DE LA ENERGIA (EVE)
The Ente Vasco de la Energía (EVE) is the Basque Country's energy agency, a public body established
by the Basque Government. EVE serves as a central force in the region's energy sector, with a focus
on the promotion of energy efficiency, the expansion of renewable energy sources, the development
of sustainable energy policy, and the advancement of innovative energy technologies. The funding
has been provided through the Grants programme for investment in the demonstration and validation
of emerging marine renewable energy technologies 2023 to further support the ACHIEVE Programme.
Share your feedback
Discover