ACHIEVE Project Objectives Presentation
Released
Released
Announcement PDF
ACHIEVE Programme
Objectives
Validating next-generation CETO technology and its commercial
potential through the 80 kW ACHIEVE demonstrator
CARNEGIE CLEAN ENERGY
ACHIEVE PROGRAMME CONTEXT
A first-of-a-kind offshore demonstration
80 kW
rated, ½ physical scale ACHIEVE CETO
demonstrator unit
Time invested up front
To ensure a strong result, extra time is going to engineering validation,
operational readiness, installation planning and integration.
Meaningful performance data
The aim is safe deployment and valuable real-world data from the
demonstration at sea.
Commercial objectives
Modular, fully submerged, all-weather generation for modern markets.
02
Simple as possible, but not simpler
We believe that economic solutions need high energy extraction
for the capital expended. CETO balances simplicity with
performance and commercial viability.
AC HI E VE PROGR AM M E: DEM ONST R AT I NG CO M M ERCI AL, T ECHNIC AL AN D O PER AT IO N AL OBJECT IVES FO R CO M M ERCI AL- S C A LE CET O
Six CETO objectives
01 Commercial objectives Modular, scalable and accepted due to fully submerged design
02 Energy capture Capacity factors and spatial density
03 Control system AI-enabled algorithms working in real conditions
04 Survivability and reliability Active and passive mitigation strategies in extreme seas
05 Operations and maintenance Rapid generator module swaps with minimal offshore work
06 Technology development Multi moorings, continuous depth control, rotary power conversion
03
OBJECTIVE 01
Commercial objectives
ACHIEVE will validate features designed to reduce lifecycle costs, simplify deployment
and maintenance, support large-scale manufacturing and maximise community support.
Modular architecture
Aims to ease fabrication, transport, assembly and
integration using existing industrial supply chains and
port infrastructure.
Potential for scalable manufacturing, flexible logistics
and simpler installation with smaller vessels.
Fully submerged operation
Operates completely beneath the surface to enhance
safety in storms and avoid visual impact from shore,
minimising the social licence impediment seen in
offshore wind.
04
OBJECTIVE 02 · CAPACITY FACTOR
Energy capture and power conversion
30–50%
expected capacity factor range for future
commercial scale deployments
What ACHIEVE will test
The power production of CETO, validating models showing
commercial deployments can achieve capacity factors
consistent with pre-deployment modelling.
Where it applies
Selected sites in Spain, Portugal, France, UK, Ireland, Australia,
the United States and other comparable wave resources.
Potential upside
Higher capacity factors are possible as control algorithms
improve.
05
Capacity factor = average production / capacity
OBJECTIVE 02 · SPATIAL DENSITY
More energy from a smaller footprint that’s hidden from view
CETO Commercial (forecast)
30 MW/km²
Offshore wind (typical)
6 MW/km²
ACHIEVE energy production data will support validation of the spatial density forecasts.
06
OBJECTIVE 03
Advanced control system evaluation
Algorithms designed to optimise
power capture while managing
structural and operational loads will
be tested in the real ocean.
HPE collaboration
Joint work shaped the control algorithm design
AI – Reinforcement learning and machine learning
Controller that learns and wave predictor demonstrated
Real-world data
Valuable, hard-to-attain data collected and analysed
07
OBJECTIVE 04
Survivability and reliability
A range of active and passive strategies are built into the CETO design and will be
demonstrated.
Extreme seas
Survivability strategies come
into play
Position adjusts
The system moves within the
water column
Output continues
Integrity is maintained while
still generating electricity
Managing the power of the ocean has been part of CETO’s core architecture since inception. It has shaped design,
control and operations and maintenance strategies.
08
OBJECTIVE 05
Operations and maintenance
Maintenance within existing port infrastructure, with minimal offshore intervention.
Quayside PTO swaps
Power take-off and electrical
modules are rapidly removed and
installed at the quay
Structure stays put
The primary structure remains in
the water, avoiding big lifts
Fewer offshore needs
Reduced reliance on large,
specialised vessels and no divers
The goal is to show that rapid and low-cost maintenance is feasible, reducing downtime and improving operational
availability.
09
OBJECTIVE 06
Technology development progress
2019
Digital Development pathway
A strategic step back in TRL that
delivered step-change improvements.
2026
ACHIEVE Programme
Demonstrating multiple moorings,
rotary PTO and advanced control.
10
2015
Earlier CETO generations
Prior deployments reached
TRL 7/8.
COMMERCIAL PATHWAY
From design advances to funding
TOP RANKED EUROPEWAVE
PROGRAMME POSITION
Design advances developed during the Digital
Development Pathway unlocked CETO’s top ranking
and the cornerstone funding for ACHIEVE.
ACHIEVE is generating data for cost of energy
assessments. The initial economic modelling was
reviewed and verified by an independent expert to
win EuropeWave funding.
The deployment is optimised to meet multiple technical objectives within the scope and budget of ACHIEVE.
11
SUPPORTING COST OF ENERGY
ASSESSMENT
MARKET CONTEXT
Aligned with Europe’s ocean energy goals
1 GW
of installed EU ocean energy capacity by
2030
40 GW
of installed EU ocean energy capacity by
2050
Carnegie is developing plans for a 6MW project at BIMEP in Spain.
Business model demonstrates revenues 3-4 years prior to commercial project commissioning.
Additional opportunities with Defence and Data Centres.
12
Europe remains the primary target market. Carnegie also actively engages with other jurisdictions with
suitable wave resources, energy market conditions and customer requirements.